- Once you order a dedicated fiber circuit (e.g. 100x100), the ISP will deliver fiber to your location and a team of field personnel will visit during the installation process
- An Outside Plant Engineer will assess the best fiber entry point and check for any additional requirements
- A construction technician will install the fiber, you may or may not see them depending on their need for access
- A third technician will splice the fiber and install the Network Interface Device (NID)
- An installation technician will complete the circuit installation, public IPs will be sent if required
- The "completion date" is when your service is turned on and billing begins, with splicing set for a date before the physical circuit installation
- SOL Communications will communicate regularly with the ISP's project manager and inform your MSP or IT staff of any information to ensure a smooth installation process, at no extra cost to you
- You pay a monthly fee for the circuit, the same as you would if you went directly to the ISP.